Irving Oil HQ
10 King Square South Saint John, NB
13 Storeys
General Contractor: FCC/EllisDon
Architect: B+H
Pro-Bel services provided: Design, Engineer, Manufacture, Supply and Install


Pro-Bel Technical Solution
We designed a conventional davit and anchor system, a monorail for window washing purposes, and a horizontal lifeline system for fall protection. Wall anchors around the perimeter of the 12th and 4th floor roofs and recessed terrace anchors on the 5th floor terrace provide access to much of the façade. Davits on the 12th floor provide access to the midsections of the eastern and western facades. Two parallel monorail tracks are fitted in the interior on either side of the skylight; these will provide access interior access to not only the skylight but the walls as well. The horizontal lifeline (cable) system is installed around the perimeter of the main roof for safe access to fall hazard zones (restrictive areas) at the roof edge.